Work on €55m Letterkenny project ‘flying’

THE new Letterkenny Wastewater Treatment Plant is ahead of schedule and due to be completed and operational by the end of this year, it was confirmed this week.
Senior Engineer Mr Fitz Howard told a meeting of the Letterkenny Electoral Area committee that progress on the €55 million project is “flying” and suggested that members visit the site to see the great work being done there.
Construction commenced on the site at Magheranan on May 3rd, last year. And to date, the main reinforced concrete treatment units and pumping stations are all substantially complete.
Senior Engineer Mr Fitz Howard told a meeting of the Letterkenny Electoral Area committee that progress on the €55 million project is “flying” and suggested that members visit the site to see the great work being done there.
Construction commenced on the site at Magheranan on May 3rd, last year. And to date, the main reinforced concrete treatment units and pumping stations are all substantially complete.