Advertisement

Milestone reached as final turbine installed at Lenalea Wind Farm

A new wind farm project in Donegal could be fully operational by November, following the installation of its final turbine last week.

Lenalea Wind Farm has reached a landmark milestone in its construction with the successful installation of its seventh and final turbine at the site located around 10k south west of Letterkenny.

This milestone follows ongoing, close collaboration with EirGrid, which has completed commissioning and energisation of Lenalea’s 110kV substation, resulting in the site now being connected to the national transmission system.

Advertisement

The connection to the grid paves the way to the commissioning of the turbines.

The commissioning and testing of the turbines will take place from August to October 2023, following which it is anticipated to have the site fully operational in November 2023.

The 30.1MW onshore wind project is a joint venture between SSE Renewables and FuturEnergy Ireland.

Once operational, the site could power up to 20,000 Irish homes each year and offset 24,500 tonnes of carbon per annum, contributing to the delivery of Ireland’s 2030 renewable energy targets.

Lenalea’s first turbine was installed on 23 June with the seventh and final turbine successfully installed last Wednesday, August 9.

Vestas has supplied and installed all seven V117-4.2 MW turbines, which have been boosted to a rated capacity of 4.3MW for the project.

SSE Renewables, the lead developer on the project, will also be responsible for the management of Lenalea in the operations phase, which is scheduled to commence in late 2023.

Advertisement

A Community Fund Fund will be available once the project becomes operational.

The delivery of Lenalea Wind Farm represents a joint total capital investment of more than €40 million by development partners SSE Renewables and FuturEnergy Ireland.

Ghislain Demeuldre, SSE Renewables’ Head of Onshore Development for Ireland, said:

“Installing the final turbine at Lenalea is a landmark moment in the delivery of this project and particularly satisfying when this coincides with the grid connection.

“It is testament to the commitment by our project team as well as by our project’s supply chain partners from Adman who turned the first sod, OMEXOM who built the substation, EirGrid and ESBN who commissioned the substation and finally turbine supplier Vestas supported on the ground by Glenturas.

“They all have worked tirelessly since day one to reach this important milestone. We are also particularly grateful for their dedication to safety as everyone involved on site to date was able to get home injury-free. We are now on track to enter commercial operation later this year.”

Elizabeth Anne Read, Vestas Associate Project Manager for the Lenalea wind project, said:

“It is a proud moment to see all the turbines installed on time which is a testament to the great collaboration between all stakeholders involved. This is just the latest in a number of exciting onshore renewable energy projects in our Irish pipeline, all of which will make an important contribution to the country’s 2030 targets.”

Receive quality journalism wherever you are, on any device. Keep up to date from the comfort of your own home with a digital subscription.
Any time | Any place | Anywhere

SUBSCRIBE TO CURRENT EDITION TODAY
and get access to our archive editions dating back to 2007
(CLICK ON THE TITLE BELOW TO SUBSCRIBE)
Every Thursday
Every Monday
Top
Advertisement

Donegal News is published by North West of Ireland Printing & Publishing Company Limited, trading as North-West News Group.
Registered in Northern Ireland, No. R0000576. St. Anne's Court, Letterkenny, County Donegal, Ireland