Advertisement

Construction set to commence on €31 million investment in Buncrana and Ballybofey/Stranorlar Sewerage Scheme

Uisce Éireann, working in partnership with Donegal County Council, are set to start works as part of a €31 million investment to upgrade the wastewater infrastructure in Buncrana, Ballybofey and Stranorlar.

The works is part of the sewerage scheme will result in significant improvements to water quality in Lough Swilly and the River Finn by eliminating storm water overflows, safeguarding the environment and supporting social and economic development.

The Buncrana and Ballybofey/Stranorlar Sewerage Scheme will commence in two phases, with construction starting  in Ballybofey and Stranorlar in March with the second phase of the works in Buncrana to commence at the end of April.

Advertisement

The sewerage scheme is a significant development for the town of Ballybofey and Stranorlar, which will see knock-on benefits to the local natural environment of the River Finn, as well as supporting the social and economic development of the town.

Uisce Éireann’s Regional Lead Eunan Canavan said the scale of investment in Donegal and delivery of this critical infrastructure in Ballybofey and Stranorlar is hugely significant.

“We are investing approximately €100m in Donegal as part of the delivery of a number of strategic projects as we strive to deliver best in class wastewater services and infrastructure for Ireland now and in the future.

“We are delighted to see years of hard work in the planning and development of this sewerage scheme realised as we start to break ground in Ballybofey and Stranorlar. Eliminating non-compliant storm overflows into the River Finn, reducing the risk of overflows during storms, as well as supporting the social and economic development of Ballybofey and  Stranorlar into the future is a key priority for Uisce Éireann. This project is critical in safeguarding the environment as well as future-proofing the infrastructure in Ballybofey and Stranorlar,” he said.

Eunan said this sewerage scheme will not only improve water quality in the River Finn it will also ensure compliance with Urban Wastewater Treatment Regulations 2001 and the EPA Wastewater Discharge Licencing.

“Having cleaner water will also enhance the areas’ amenity value. We will continue to work closely with the local community and will issue further updates as we progress with this vital project,” he said.

The works will include the replacement of the existing pumping station at Navenny and upgrades to the existing St Joseph’s Pumping Station and Glenfinn Road Pumping Station.

Advertisement

Approximately 2km of sewer network will also be upgraded to increase capacity, allowing for current and future population growth of the town.

The works will also include the decommissioning of two existing storm overflows.

Residents and visitors to Ballybofey and Stranorlar will see works taking place along Chapel Lane, Stranorlar Main Street, Navenny Road, Chestnut Road and St Joseph’s Pumping Station. During the works traffic management will be in place however local and emergency access will be maintained at all times.

The works will be carried out by Ward & Burke Water Limited on behalf of Uisce Éireann.

The works which are due to commence in March 2023, will be completed by the end of 2024.

Receive quality journalism wherever you are, on any device. Keep up to date from the comfort of your own home with a digital subscription.
Any time | Any place | Anywhere

SUBSCRIBE TO CURRENT EDITION TODAY
and get access to our archive editions dating back to 2007
(CLICK ON THE TITLE BELOW TO SUBSCRIBE)
Every Thursday
Every Monday
Top
Advertisement

Donegal News is published by North West of Ireland Printing & Publishing Company Limited, trading as North-West News Group.
Registered in Northern Ireland, No. R0000576. St. Anne's Court, Letterkenny, County Donegal, Ireland